Construction Schedule
While most improvements are complete for the La Crescenta Avenue Rehabilitation Project, certain key elements – including roadway resurfacing, striping and decorative crosswalks – are scheduled for completion by June 2026, barring any additional unforeseen circumstances.
The revised schedule is due to utility relocation work required by GWP Electric, Charter and AT&T for the Twelve Oaks development site on La Crescenta Avenue and Sycamore Avenue.
The City remains committed to delivering a high-quality project that meets the long-term needs of the community and appreciates the public’s continued patience and cooperation throughout the construction process.
Tentative Construction Schedule:
- April 2026: Roadway resurfacing
- May 2026: Roadway striping and utility adjustments
- June 2026: Installation of decorative crosswalks and reflective pavement on Paloma Avenue
From the City of Glendale – Public Works