UPDATE La Crescenta Avenue Rehabilitation Project

The La Crescenta Avenue Rehabilitation Project has made significant progress in recent months. Major safety improvements have been implemented, including the realignment of intersections and enhanced pedestrian accessibility. Additionally, the contractor has completed installation of bio-retention facilities and critical infrastructure upgrades, including traffic signal and fiber optic systems, as well as the upsizing of existing sewer mainline.

While most improvements are complete, certain key elements – including the final paving, striping and decorative crosswalks – are scheduled for completion by March 2026, barring any additional unforeseen circumstances.

  The revised schedule is due to unforeseen conflicts encountered during underground utility work and longer-than-anticipated lead times for the delivery of traffic signal materials. Installation and commissioning of traffic signal poles must be completed before paving and striping improvements can begin, as the new striping layout incorporates additional crossings to improve pedestrian and cyclist safety.

The City remains committed to delivering a high-quality project that meets the long-term needs of the community and appreciates the public’s continued patience and cooperation throughout the construction process.

Tentative Construction Schedule:

  • February 2026: Final paving and adjustment of utilities
  • March 2026: Striping installation including lane reconfiguration to establish one travel lane in each direction, a center turn lane and bike facilities such as buffered bike lanes and protected bike lanes throughout the corridor. Installation of decorative crosswalks and cool pavement on Paloma Avenue.

Impacted Streets

During the construction period, detours, intermittent lane closures and traffic delays are expected on the following streets:

Location and Dates

  • La Crescenta Avenue at Urquidez Avenue: Travel lanes may be closed intermittently between Jan. 19 thru Jan. 30 (excludes weekends and holidays)
  • La Crescenta Avenue at Montrose, Honolulu, Roselawn, Oakmont View, Piedmont, Shirlyjean, and midblock between Arlington and Las Palmas: Travel lanes may be closed intermittently between Jan. 19 thru Jan. 30 (excludes weekends)

  Description of Work

  • Contractor performing sanitary sewer main repairs.
  • Contractor performing storm drain upgrades.
  • Contractor traffic signal upgrades.

  Please observe posted construction signage and drive safely near construction zones.

*Construction activity and closures are subject to change.